Critical Care Hospital - Case Study _
Incident for Discussion: Critical Care Hospital Critical Care Hospital has
planned to purchase a CATSCAN within the next six months. Though not mentioned
in the text, the cost of the equipment will be at least several hundred
thousand dollars, and could even ex ....
Middle of paper
.... waiting time for the CATSCAN is five
months. This leaves the PM eight months to accomplish her goal. Given that the
equipment is arriving simultaneously with the onset of the construction
project, I would suggest a combination of a heuristic approach using an \\"As
Late As Possible\\" (\\"ALAP\\") prioritization with a fast-track approach to the
actual constructionThe reason for the ALAP approach is the five-month delay
prior to the equipment being delivered. Holding off on allocating resour ....
------------------